Utilisation depends on what counts as available time. State the definition before using the percentage in a capacity decision.
Checks that answer this question
- Define the observation window.
- Record productive operating time.
- Separate planned unavailability, waiting and faults.
Worked planning example
For example, 90 minutes of productive operation within a defined 120-minute available window gives 75% utilisation. A different availability definition changes the result.
Decision and acceptance check
Review queueing, accepted output and process limits alongside utilisation. A higher percentage is not automatically better if it creates congestion or poor results.
Record the evidence
Use one row per observation rather than combining several different conditions. Record window, availability definition, productive time, waiting time and accepted output. Keep the original entry when adding the follow-up so that the change remains visible. If a field cannot be verified, mark it unknown and assign someone to resolve it before treating the record as complete.
Product and process boundaries
Keep assumptions visible and distinguish measured results from estimates. Compare the same scope, workload and time period before drawing a commercial conclusion. Include labour, rework, storage and service constraints where they affect the decision. Planning examples are hypothetical and do not represent quotations or guaranteed savings. Confirm current commercial terms directly with the supplier. The useful outcome is a decision someone can review later using the original inputs, not a precise-looking total built from uncertain figures.
Related guidance and product support
Continue with our cleaning budget planning. For product or equipment suitability, explore equipment and supply support and contact Aspin with the details of your operation.